When reservoir is full on upstream side, the maximum stress comes upon__________________?
Correct answer: C. Bottom of dam
- A. Top of dam
- B. Face of dam
- C. Bottom of dam
- D. All are correct
Explanation
Hydrostatic water pressure increases with depth, so the greatest lateral water pressure and resulting stress occur near the bottom of the dam. The top experiences the least water pressure.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Irrigation and Water Management
262 free Irrigation and Water Management MCQs from Agriculture, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Agriculture questions like this
Agriculture is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Irrigation and Water Management questions
Tanda dam is constructed on river ___________________?
Water storage efficiency in the root zone depends upon__________________?
Water available in root zone of plants, is about 50% of soil moisture content. which is always available to the plants is called________________?
The steep conduits made in the body of dam for running turbines to generate hydro-electric power are called__________________?
The resultant pressure of water on the face of dam is equal to ____________________ ?
Always flow inside the ground is ____________________?