What is the defining feature of selective tendering in construction procurement?
Correct answer: B. Only selected qualified contractors are invited to tender
- A. Every contractor in the market is invited without screening
- B. Only selected qualified contractors are invited to tender
- C. The contract is awarded without comparing any submitted price
- D. The client purchases materials without appointing a contractor
Explanation
Selective tendering restricts invitations to contractors who meet stated qualification or experience requirements. It differs from open tendering, where any eligible contractor may generally submit a bid subject to the tender conditions.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
About Construction Management and Estimation
Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.
Practise Construction Management and Estimation
80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Construction Management and Estimation questions
What is the main purpose of a construction cash flow forecast?
Which item is normally included in a contractor's site overhead?
In valuation, what does the capitalization method primarily use to estimate property value?
Which scheduling technique uses probabilistic activity durations to estimate the likely completion time of a construction project?
A revised estimate for a public works project is generally prepared when:
What does an abstract of cost in a construction estimate normally present?