What assess the risk and your plans for risk mitigation and revise these when you learn more about the risk ?
Correct answer: A. Risk monitoring
- A. Risk monitoring
- B. Risk planning
- C. Risk analysis
- D. Risk identification
Explanation
Risk monitoring repeatedly checks identified risks, evaluates whether their impact or likelihood has changed, and updates mitigation plans as new information appears. Planning and analysis occur earlier, while monitoring continues throughout the project.
Last updated
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
Related questions
A graphical technique for finding if changes and variation in metrics data are meaningful is known as_________________?
A __________ is a measure, an intangible measure, which is difficult to count in clear terms?
A _______________ is developed using historical cost information that relates some software metric to the project cost ?
A listing of the names and addresses of all the employees for an organization would be an example of a(n)_________________________?
A make-buy decision is based on whether________________?