What assess the risk and your plans for risk mitigation and revise these when you learn more about the risk ?

Correct answer: A. Risk monitoring

  • A. Risk monitoring
  • B. Risk planning
  • C. Risk analysis
  • D. Risk identification

Explanation

Risk monitoring repeatedly checks identified risks, evaluates whether their impact or likelihood has changed, and updates mitigation plans as new information appears. Planning and analysis occur earlier, while monitoring continues throughout the project.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Software Project Management

171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Software Project Management questions