Water is flowing through a series of four tanks and getting heated as shown in figure. It is desired to design a cascade control scheme for controlling the temperature of water leaving the tank 4 as there is a disturbance in the temperature of a second stream entering the tank 2. Select the best place to take the secondary measurement for the second loop?

Correct answer: A. Tank 3

  • A. Tank 3
  • B. Tank 2
  • C. Tank 1
  • D. Tank 4

Explanation

The secondary sensor should detect the disturbance before it significantly affects the primary outlet temperature, while still being downstream of the disturbance entry point. Tank 3 provides this earlier measurement, leaving tank 4 as the primary measurement point.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Process Control and Instrumentation

254 free Process Control and Instrumentation MCQs from Chemical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Chemical Engineering questions like this

Chemical Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Process Control and Instrumentation questions