The difference between actual result and corresponding amount of flexible budget, on the basis of actual level of output is classified as ____________?

Correct answer: C. flexible budget variance

  • A. sales mix variance
  • B. sales volume variance
  • C. flexible budget variance
  • D. static budget variance

Explanation

A flexible budget is adjusted to the actual output level, so the remaining difference between actual performance and that adjusted budget is the flexible budget variance. Static budget variance instead compares actual results with the original budget at planned output.

Written and checked by , editorLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Cost Accounting

Cost accounting measures and analyses the cost of producing goods or providing services for planning, control and pricing decisions. It covers direct and indirect costs, fixed and variable costs, job and process costing, break-even analysis, marginal costing, overhead allocation, and the difference between product cost and period cost.

Practise Cost Accounting

941 free Cost Accounting MCQs from Accounting, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Accounting questions like this

Accounting is on 2 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Cost Accounting questions