Sometimes, batch process is preferred over continuous process, when the product___________________?

Correct answer: A. Both A. & B.

  • A. Both A. & B.
  • B. Sales demand is fluctuating
  • C. Quality & yield cannot be achieved in continuous processes, because of long residence time
  • D. Neither A. nor B.

Explanation

Batch operation is advantageous when demand varies because production can be started or stopped without continuously operating a large plant. It is also selected when the required product quality or yield is difficult to obtain in continuous operation.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Plant Design and Economics

803 free Plant Design and Economics MCQs from Chemical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Chemical Engineering questions like this

Chemical Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Plant Design and Economics questions