SMI = [Mt - (Fa + Fc + Fd)]/Mt. Here Mt is the number of modules______________?
Correct answer: A. in the current release
- A. in the current release
- B. in the current release that have been changed
- C. from the preceding release that were deleted in the current release
- D. none of the mentioned
Explanation
In the SMI formula, Mt is the total number of modules in the current release; Fa, Fc, and Fd then account for additions, changes, and deletions. Thus Mt is not limited only to modules that changed.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Testing and Quality Assurance
181 free Software Testing and Quality Assurance MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Testing and Quality Assurance questions
Architectural Design Metrics are ______________ in nature ?
How many Information Domain Values are used for Function Point Computation ?
Which of the following is not a metric for design model ?
Structural complexity of a module i is given as S(i) = f*f (i). What does f symbolizes here ?
Function Point Computation is given by the formula___________________?
Statement and branch coverage metrics are part of______________________?