Screen capacity is expressed in terms of____________________?

Correct answer: D. tons/hr-ft2

  • A. tons/hr
  • B. tons/ft2
  • C. Both A. & B.
  • D. tons/hr-ft2

Explanation

Screen capacity must indicate both the mass processed per unit time and the screening area available, so it is expressed as tons per hour per square foot. Tons per hour alone gives throughput but not capacity per unit area.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

Practise Chemical Process Principles

2,710 free Chemical Process Principles MCQs from Chemical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Chemical Engineering questions like this

Chemical Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Chemical Process Principles questions