Routing in production, planning & control is concerned with the___________________?

Correct answer: B. Sequence of operation to be performed

  • A. Progress of work performed
  • B. Sequence of operation to be performed
  • C. Authorisation of work to be performed
  • D. Balancing of load on machines

Explanation

Routing establishes the path of manufacture by specifying the sequence of operations, machines and work centres through which a job must pass. Progress monitoring belongs to dispatching or follow-up, not routing.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Plant Design and Economics

803 free Plant Design and Economics MCQs from Chemical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Chemical Engineering questions like this

Chemical Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Plant Design and Economics questions