Permissible velocity of water flowing through concrete lined tunnel is usually __________________?
Correct answer: B. 4 - 5m/sec
- A. 3 - 4m/sec
- B. 4 - 5m/sec
- C. 5 - 6m/sec
- D. 6 - 7m/sec
Explanation
Concrete lining reduces seepage and protects the tunnel from erosion, allowing a relatively high permissible velocity. A usual design range is about 4 to 5 m/sec.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Irrigation and Water Management
262 free Irrigation and Water Management MCQs from Agriculture, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Agriculture questions like this
Agriculture is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Irrigation and Water Management questions
Estimated quantity of global water is __________which covers about 70% of earth?
_________% of total global water is fresh and its major portion is obtained from Rains ?
The discharge of a well per unit draw down usually expressed as gallons or liters per minute is called ____________________?
A type of flow in which water particles, while moving in the direction of flow, rotate about their mass centre is called _________________?
velocity of gases is measured with a _____________________?
The hydraulic gradient line (H.G.L)represents the sum of_________________?