Lead is poured into the joints between two ___________________ pipes?

Correct answer: A. Cast iron

  • A. Cast iron
  • B. Steel
  • C. Concrete
  • D. Plastic

Explanation

Traditional cast-iron pipe joints are sealed by pouring molten lead into the annular space and then caulking it. This method is known as a lead-caulked or lead-jointed connection.