Lead is poured into the joints between two ___________________ pipes?
Correct answer: A. Cast iron
- A. Cast iron
- B. Steel
- C. Concrete
- D. Plastic
Explanation
Traditional cast-iron pipe joints are sealed by pouring molten lead into the annular space and then caulking it. This method is known as a lead-caulked or lead-jointed connection.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
Practise Fluid Flow Operations
909 free Fluid Flow Operations MCQs from Chemical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Chemical Engineering questions like this
Chemical Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Fluid Flow Operations questions
Friction factor for fluid flow in pipe does not depend upon the________________?
Hydro-cyclone is a____________________?
Which of the following does not discharge the dust collected as a dry solid?
The most economical channel section for the fluid flow is the one for which the discharge is maximum for a given cross-sectional area. Vertical velocity distribution in an open channel for laminar flow can be assumed to be_______________?
Pressure required to increase the density of water by about 1% is ____________________ atmosphere?
As the fluid flow rate increases, the float of the Rotameter____________________?