In levelling, the difference between the first and last reduced levels in a run should equal which quantity?

Correct answer: C. The sum of rises minus the sum of falls

  • A. The sum of all backsights
  • B. The sum of all foresights
  • C. The sum of rises minus the sum of falls
  • D. The sum of rises plus the sum of falls

Explanation

The change in reduced level equals total rises minus total falls. This provides the arithmetic basis for checking a levelling calculation independently of the height of instrument method.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Surveying

Surveying covers measurement of distances, angles and elevations, traversing, levelling, contouring, plane table work, theodolites, total stations and basic photogrammetry. It includes error adjustment, coordinate calculations, area and volume determination, and the distinction between accuracy and precision, as well as between temporary and permanent adjustments.

Practise Surveying

77 free Surveying MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Civil Engineering questions like this

Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Surveying questions