In highway route location, which survey is conducted first to identify broad alternative corridors?
Correct answer: C. Reconnaissance survey
- A. Final location survey
- B. Preliminary survey
- C. Reconnaissance survey
- D. Construction staking survey
Explanation
A reconnaissance survey examines the terrain, obstacles, settlements and broad route possibilities. Preliminary and final location surveys are carried out later with progressively greater detail.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
About Transportation Engineering
Transportation engineering covers highway planning and alignment, traffic studies, road geometric design, pavement materials and flexible or rigid pavement construction. It also includes railway, airport and traffic engineering concepts such as sight distance, superelevation, signals, capacity and level of service, distinguishing pavement failure from poor geometric design.
Practise Transportation Engineering
80 free Transportation Engineering MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Transportation Engineering questions
In highway planning, a desire-line diagram is mainly used to show:
Which pavement distress is most directly associated with inadequate drainage of a flexible pavement?
A taxiway at an airport primarily provides a route for aircraft between the:
Average Annual Daily Traffic, or AADT, is obtained by dividing the annual traffic volume by the:
If the average time headway between vehicles in a traffic lane is 3 seconds, the corresponding flow rate is approximately:
Stripping in an asphalt pavement most directly refers to the: