In accounting, the cost which is predicted to be incurred or future cost is known as ________?

Correct answer: C. budgeted cost

  • A. past cost
  • B. incurred cost
  • C. budgeted cost
  • D. actual cost

Explanation

A budgeted cost is a cost expected or planned to be incurred in the future. Actual or incurred cost refers to expenditure that has already occurred, while past cost is historical cost.

Written and checked by , editorLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

About Cost Accounting

Cost accounting measures and analyses the cost of producing goods or providing services for planning, control and pricing decisions. It covers direct and indirect costs, fixed and variable costs, job and process costing, break-even analysis, marginal costing, overhead allocation, and the difference between product cost and period cost.

Practise Cost Accounting

941 free Cost Accounting MCQs from Accounting, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Accounting questions like this

Accounting is on 2 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Cost Accounting questions