If the difference between costs linked to highest and lowest observation of cost driver is $36000 and observation of cost driver is 30 machine hours, then slope coefficient would be __________?

Correct answer: A. $1,200

  • A. $1,200
  • B. $1,400
  • C. $1,600
  • D. $1,800

Explanation

The slope coefficient equals the change in cost divided by the change in machine hours: $36,000 ÷ 30 = $1,200 per machine hour. Thus option a gives the variable cost rate.

Written and checked by , editorLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Cost Accounting

Cost accounting measures and analyses the cost of producing goods or providing services for planning, control and pricing decisions. It covers direct and indirect costs, fixed and variable costs, job and process costing, break-even analysis, marginal costing, overhead allocation, and the difference between product cost and period cost.

Practise Cost Accounting

941 free Cost Accounting MCQs from Accounting, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Accounting questions like this

Accounting is on 2 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Cost Accounting questions