Gantt charts are used for streamlining the__________________?

Correct answer: B. Production schedule

  • A. Inventory control
  • B. Production schedule
  • C. Sales forecasting
  • D. Quality control

Explanation

A Gantt chart displays activities against time, showing their sequence, duration, overlap and progress. This makes it primarily a tool for planning and streamlining the production schedule.