During open circuit test of a transformer:
Correct answer: A. primary is supplied rated voltage
- A. primary is supplied rated voltage
- B. primary is supplied full-load current
- C. primary is supplied current at reduced voltage
- D. primary is supplied rated kVA
Explanation
The open-circuit test is performed at rated voltage so that the normal operating core flux and core loss are produced. Since the secondary is open, only a small magnetising current flows.
Last updated
Practise Electrical Machines
1,061 free Electrical Machines MCQs from Electrical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Electrical Engineering questions like this
Electrical Engineering is on 2 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
Related questions
The typical value of SCR for modern alternator is____________?
If the efficiency of a machine is to be high, what should be low __________?
Which of the following does not change in a transformer ?
In a transformer the energy is conveyed from primary to secondary_________?
A transformer core is laminated to__________?