Debt-re-scheduling is ?
Correct answer: B. a change in debt repayment due to inability to pay
- A. an agreement with the World Bank to turn some of a debt into other forms
- B. a change in debt repayment due to inability to pay
- C. regular payments of interest and repayments of capital
- D. a program of austerity measures agreed with the IMF to make repayment possible
Explanation
Debt rescheduling changes the timing or terms of repayment, usually because the borrower cannot meet the original schedule. It is not the same as routine interest and principal payments or a complete debt conversion.
Last updated
About Macroeconomics
The economy is studied as a whole through national income, gross domestic product, inflation, unemployment, economic growth and business cycles. Coverage includes aggregate demand and supply, consumption and investment, money and banking, fiscal and monetary policy, exchange rates and balance of payments, which distinguishes macroeconomics from the study of individual markets.
Practise Macroeconomics
1,462 free Macroeconomics MCQs from Economics, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Economics questions like this
Economics is on 2 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
Related questions
1. The most widely traded currency in the foreign exchange market is the ?
85% of the world's population lives in developing countries and receives about _____ of the world's income?
A 44-nation survey regrading religions found that_________________?
A bank has excess reserves to lend but is unable to find anyone to borrow the money This will _________ the size of the money multiplier?
A capital account surplus might be expected to cause a current account deficit because the associated ?