A worker has a time rate of 15/hr. He makes 720 units of component (standard time : 5 minutes/ unit) in a week of 48 hours. His total wages including Rowan bonus for the week is

Correct answer: D. 864

  • A. 792
  • B. 820
  • C. 840
  • D. 864

Explanation

Standard time for 720 units is 60 hours, giving 12 hours saved; Rowan bonus is 12/60 × 48 × 15 = 144. Adding this to basic wages of 48 × 15 = 720 gives total wages of 864.

Written and checked by , editorLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Cost Accounting

Cost accounting measures and analyses the cost of producing goods or providing services for planning, control and pricing decisions. It covers direct and indirect costs, fixed and variable costs, job and process costing, break-even analysis, marginal costing, overhead allocation, and the difference between product cost and period cost.

Practise Cost Accounting

941 free Cost Accounting MCQs from Accounting, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Accounting questions like this

Accounting is on 2 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Cost Accounting questions