A detailed construction estimate is normally prepared using which basis?

Correct answer: B. Completed drawings, specifications, and measured quantities

  • A. A rough project description and an assumed profit margin
  • B. Completed drawings, specifications, and measured quantities
  • C. The contractor's previous invoice and current bank balance
  • D. The site area alone and a general market allowance

Explanation

A detailed estimate is based on developed drawings, technical specifications, quantity take-off, and analysed rates. A rough project description is more appropriate for an early preliminary estimate, not a detailed one.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Construction Management and Estimation

Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.

Practise Construction Management and Estimation

80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Civil Engineering questions like this

Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Construction Management and Estimation questions