A tank is filled by three pipes with uniform flow. The first two pipes operating simultaneously fill the tank in the same during which the tank is filled by the third pipe alone. The second pipe fills the tank 5 hours faster than the first pipe and 4 hours slower than the third pipe. The time required by the first pipe is?
Correct answer: C. 15 hrs
- A. 6 hrs
- B. 10 hrs
- C. 15 hrs
- D. 30 hrs
Explanation
Let the first pipe take x hours, so the second takes x - 5 hours and the third takes x - 9 hours. Since the first two together take the same time as the third alone, 1/x + 1/(x - 5) = 1/(x - 9); solving gives x² - 18x + 45 = 0, whose valid root is x = 15 hours. The likely mistake is choosing 10 hours by using only one of the time differences and not applying the combined-rate condition.
Last updated
About Time and Work
Problems measure work through rates, treating each person's or machine's contribution as work completed per unit time. Questions cover combined work, efficiency, wages, alternate working schedules, pipes and cisterns, and men-days relationships, with care needed to distinguish time taken by one worker from the time required when workers act together.
Practise Arithmetic
1,060 free Arithmetic MCQs from Mathematics, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Mathematics questions like this
Mathematics is on 67 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
Related questions
15 men can build a 500m long wall in 30 days. In how many days can 30 men build a 1.2 km long wall?
2 men and 12 women can finish a job in 4 days. 4 men and 6 women can do the same job in 5 days. Find the time taken by 1 man and 1 woman to complete the job.
3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to complete the same work . In how many days will 10 women complete the same work?
4 men and 2 woman can complete a work in 2 days. If 2 men alone take 5 days to complete the work, find the time taken by 2 women alone to complete the work.
6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in_______days.