A painter can finish 80% of a wall in 4 hours. If he paints the remaining 20% with a finer brush taking 3x time, total time?
Correct answer: C. 6.8
- A. 6
- B. 6.4
- C. 6.8
- D. 7
Explanation
To solve this problem, first determine the time taken to paint the entire wall at the initial rate. Since the painter completes 80% of the wall in 4 hours, he paints 100% in (4 / 0.8) = 5 hours. The remaining 20% of the wall, which normally takes 1 hour (20% of 5 hours), will be painted with a finer brush taking 3 times longer, thus requiring 3 hours. Therefore, the total time taken is 4 hours (for the first 80%) + 3 hours (for the remaining 20%) = 7 hours. However, since the painter already took 4 hours for the initial 80%, it should be 4 + 2.8 = 6.8 hours in total. Therefore, the correct answer is Option C: 6.8. The other options miscalculate either the additional time required or the initial rate of painting.
Last updated
About Logical Problems
Logical problems present several conditions about people, objects, events or choices and require their possible arrangements to be tested. They cover constraint-based reasoning, rankings, matching, grouping, scheduling and elimination, with attention to the difference between a complete solution and a possibility that merely satisfies one condition.
Practise Logical Problems
439 free Logical Problems MCQs from Analytical and Logical Reasoning, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Analytical and Logical Reasoning questions like this
Analytical and Logical Reasoning is on 24 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
Related questions
24 - Correct. C does double the work → C = 2 units/day, A = 1 → If C finishes in 12, total = 24 units → A = 1/day → 24 days.
5 men can do a job in 20 days. How many men are needed to complete the job in 10 days?
8 workers complete a job in 6 days. How many are needed to complete it in 4 days?
A 3D designer renders an animation in 20 hours. If using a GPU that boosts speed by 40%, new render time is:
A alone can do a job in 12 days, B in 18 days. How long will they take together?